You’ve got a 1920s house in East Dallas, a foundation that’s gone sideways, and a contractor who just said “raise it.” Now you’re wondering who has to sign off before the first jack goes under the floor. More people than you’d guess. Dallas wants paperwork in hand before anyone lifts a structure, and skipping it costs far more than the paperwork ever will.
Which Building Permits Does Dallas Require?
House and structure raising counts as structural work, so the city expects permits before the crew mobilizes. Not after. I’ve seen a job get a stop-work notice because the owner figured a lift was “just repair,” and the crew sat idle for weeks while the paperwork caught up.
Expect to submit engineered plans showing how the house gets supported during the lift and what the new foundation looks like. That’s what a structural engineer is for. Plumbing and electrical work usually run under separate permits filed by licensed tradespeople.
Some homeowners ask about pulling everything themselves to save money. I wouldn’t on this one. One badly stacked set of cribbing and the savings disappear fast.
Landmark Districts Add a Second Approval
If you’re in a Dallas historic district, or the house itself carries landmark status, exterior changes need a Certificate of Appropriateness from the preservation side of the city. Lifting changes the porch height and the whole proportion of the street-facing front, and reviewers notice.
Picture a Junius Heights homeowner who raises the front porch eight inches and finds out afterward that nobody signed off. That’s a bad phone call.
Contact the preservation office with your address before you design anything, because one conversation tells you whether your house is covered. Plenty of old Dallas houses aren’t, which surprises people. When it does apply, approval usually needs to be in place before your building permits get issued, and it can add weeks you’ll want to know about up front.
Floodplain Lots and Utility Reconnects
If your lot sits in a mapped floodplain, raising for flood protection brings a separate floodplain review, and the target elevation comes from city rules rather than what looks right to you. Check your address against the FEMA flood map before anyone draws a thing. Honest caveat: if you’re on higher ground, this review may never touch you.
Utilities are the other piece people forget. Gas, water, and power lines all get disconnected before the lift, and each reconnection usually needs an inspection before you can turn anything back on. Dallas summers don’t help here. A house sitting on cribbing in July with no air conditioning is a rough place to wait out a delayed inspection, so schedule those inspections early.
How Long Approval Takes
Plan on several weeks for plan review, longer if a preservation board gets involved. Dallas clay is part of why. That expansive soil swells when it’s wet and shrinks when it’s dry, so reviewers look hard at the new foundation design, and a cookie-cutter drawing gets sent back.
Your contractor should file the permits and coordinate the engineer, then hand you copies of everything. If a company asks you to file them yourself, ask why.
Once work starts, inspections happen in stages and the job pauses until each one passes. A day or two per stop is typical, though I’ve had a bad week or two when the inspector’s calendar filled up. Build slack into your move-out dates.
Waiting until the house is in the air to ask about permits is the expensive way to learn. A stop-work order leaves your home sitting on cribbing through a wet North Texas spring. Du-West handles house and structure raising and walks through the paperwork side with you. When you want the best, call Du-West.
FAQ
Do I really need permits to lift my house?
Yes, you need permits. Lifting is structural work, and calling it repair won’t hold up once an inspector shows up. Call Dallas Development Services with your address and ask what applies.
My house is old. Does that make it historic?
Not automatically. Age alone doesn’t trigger review. Being inside a designated district or holding landmark status does, and the preservation office can look up your address in a few minutes.
How long before they can actually start lifting?
Several weeks is a fair planning number, more if a preservation board reviews it. Engineering comes first, so book your engineer early. Your move-out date should float until approvals clear.
Will raising it fix my cracked foundation?
Only if the new foundation fixes the cause. Dallas clay swells and shrinks with the weather, so drainage matters as much as the lift does. A raise on a bad drainage plan just moves the problem higher.
Can we stay in the house while it’s up?
Usually not. Utilities are off during the lift and the stairs are temporary at best. Most families move out for the stretch, so ask your contractor for a realistic timeframe.
Get your address pulled up with the city first. Everything else gets easier once you know what they’ll ask for.
![]()